Examples of Our Work
Bould Consulting and Gerald Katz P.C. have
worked on a wide variety of construction assignments in the English
law jurisdictions of the Caribbean, including the following:
- National Housing Corporation of Barbados,
2007. CCAS is advising the government owned Housing Corporation
on appropriate procurement methods for their low and medium cost housing
projects comprising some 293 homes
- Rotherley Construction Inc Barbados. 2007
CCAS is advising the Design/ Build contractor on all aspects of procurement
for a fast track luxury US$ 65 million luxury apartment complex on
the west coast.
- Caribbean Consultants Ltd Barbados 2007
CCAS are advising the builder/ /developer on delays and claims on
US$ 35 million Embassy in Bridgetown
- Barbados Investment & Development Corporation
and Hafeez Karamath Construction Limited, 2006 CCAS is advising
BIDC on the Design Build Newton Business Park in Barbados where significant
delays have occurred in its completion.
- Trinidad Contractors Limited and Ministry
of Works and Transport, Trinidad and Tobago 2006
CCAS is advising TCL on the programming and completion of 5# bridges
on Toco Main Road funded by IDB.
- Pres-T-Con Limited and Bouygues Batiment
Trinidad and Tobago,2006 - CCAS advised Pre-T-Con on a claim
for the piling contract to the International Waterfront Project in
Port of Spain which was successfully settled by negotiation.
- TVA Consultants Limited and Ministry of Finance,
Planning and Development, St Vincent,2006 - CCAS is providing
advice to TVA Consultants Limited in regard to their performance of
design consulting services for the Ministry of Finance, Planning and
Development in St Vincent on the National Stadium project. CCAS’
work on behalf of TVA includes analyzing TVA’s contractual obligations
and providing advice in regard to a claim for wrongful termination.
- Urban Development Corporation of Trinidad
and Tobago (Udecott) 2006. - CCAS is providing procurement
advice to Udecott on a wide range of projects with a total value in
excess of US$1billion.
- Trinidad Contractors Limited and National
Petroleum Marketing Company Limited 2006 - CCAS is advising
TCL on Extension of Time and prolongation costs on the construction
of a gas station on Tobago
- Pres-T-Con Limited and Bechtel, Trinidad
2005 - CCAS provided detailed contract analysis and preparation
of opinion on the recovery of additional costs on construction of
a jetty for a major LNG project
- Damus Limited and Bechtel, Trinidad-2004
- CCAS provided advice to Damus Limited, a specialist piping
contractor, on a substantial LNG project located in Trinidad. CCAS’s
advice has included subcontract review and assistance in regard to
a major work stoppage which has impacted Damus’s work.
- Johnston International Limited and Needham’s
Point Holdings, Ltd, Barbados, 2002 – 2004 – Katz
& Stone is providing advice and representation to Johnston International
Limited, the main contractor on the Barbados Hilton Hotel project
owned by Needham’s Point Holdings Limited. Katz & Stone’s
work on behalf of Johnston International Limited includes representing
Johnston International Limited in an arbitration initiated against
the owner of the project in regard to claims for delay, disruption
and changes in the scope of work. The form of contract is the American
Institute of Architects.
- Trinidad Contractors Ltd., and Government
of Grenada, Grenada 2003- CCAS provided an opinion supporting
the recovery of a time extension and time related costs resulting
from delays to the Gouyave Sea Defence project, the installation of
an armoured rock sea wall, caused by the failure of the Employer to
provide accurate design documents.
- Trinidad Contractors, Ltd. and Government
of British Virgin Islands, British Virgin Islands, 2003 –
CCAS provided an opinion supporting the recovery of time-related costs
under a FIDIC contract resulting from delays to construction of a
portion of the works at the Lettsome Airport, B.V.I. Our opinion extended
to an analysis of the time-related costs associated with delays to
the client’s performance and justification for the recovery
of such costs under the contract documents and principles of English
construction contract law.
- Roberts Construction & Engineering Co.
Ltd., Antigua 2003 - CCAS provided an opinion on the recovery
of loss and expense and extension of time resulting from delay in
the construction of a luxury residence in Jumby Bay, Antigua.
- Damus Limited and VA Tech Voest MCE GmbH,
Trinidad, 2003 - CCAS provided advice to and representation
of Damus Limited, a specialist piping contractor on a methanol project
located in Port Lisas, Trinidad, in connection with a dispute between
Damus and VA Tech Voest MCE GmbH over the application of contract
provisions dealing with an overrun in estimated quantities.
- Design Collaborative, Tobago Hilton Hotel,
Trinidad and Tobago 2002. - CCAS provided advice to the design
team on final cost certification and related project close-out issues.
The form of contract was American Institute of Architects.
- CO Williams Inc., Grantley Adams International
Airport, Barbados-2002 - CCAS provided the paving contractor
with an opinion on the recovery of Additional costs resulting from
delay to and disruption of the works. The form of contract was FIDIC.
- Ace Insurance Headquarters, Bermuda, 2000-2001
— Working with the owner’s representative, Katz &
Stone has provided advice and consultation relative to various construction
issues during project performance including contract negotiation and
interpretation and the analysis of claims submitted by the main contractor.
- NH International (Caribbean) Ltd v. ICS
(Grenada) Ltd – February 2001 - Provided Expert Opinion
on the appointment of the Engineer and the termination of the Contractor’s
contract by the Employer. A complex dispute under the terms of a FIDIC
contract for the construction of the National Stadium in Grenada,
West Indies. Arbitrator ruled in favour of our client NH International
(Caribbean) Ltd.
- Associated Asphalt (UK) Limited/C.O.
Williams Construction Limited v The Ministry of Tourism and International
Transport Grantley Adams International Airport Barbados–
December 2001 - Opinion on the disruption of the progress of
the works by the contractor due to the restricted possession of the
site of the works Dispute settled by negotiation.
- Sea-Land Construction Ltd. and Bermuda Underwater
Exploration Institute – April 2000 - Appointed one of
three arbitrators by Claimant, a Bermuda-based general contractor,
to decide various performance issues arising out of the construction
of a museum located in Bermuda and devoted to underwater exploration.
Issues included the impact of numerous variations on the project schedule
and the contractor’s resulting increased costs. The matter was
settled by agreement of the parties after several appearances before
the arbitrators and prior to hearings.
- NH International Ltd./ Emile Elias v. The
Government of Jamaica – January 1999 - Martyn Boud was
appointed sole arbitrator by the President of the Institution of Civil
Engineers in connection with disputes on the Montego Bay Drainage
and Flood Control project.
- Andro Electric Co., Ltd. and Noell, Inc.,
Grand Cayman, 1998 — Katz & Stone represented Andro
Electric Co., Ltd., the electrical subcontractor, in the resolution
of claims against the main contractor on the Caribbean Utilities Company
project.
- Hadsphaltic International Ltd. v Noell Incorporated
– June 1998 - Martyn Boud was appointed mediator by both
parties to resolve disputes on the C.U.C. Generating Station project.
The matter was settled by the parties following extensive mediation,
meetings and negotiation.
- BCM-Cape v. Pemberton Resorts, Inc. – January 1993
- Appointed as expert witness by BCM-Cape (Turks and Caicos Limited),
construction manager, in connection with the arbitration of disputes
arising out of construction of the Grand Palazzo Hotel in St. Thomas,
U.S. Virgin Islands. Called to testify as an expert by the Claimant
on various construction performance issues including the impact of
variations on the contractor’s costs and schedule and to prepare
a forensic accounting analysis of the employer’s counterclaim
seeking to recover major cost overruns. After 43 days of arbitration
hearings, the arbitrators awarded Claimant the entirety of its claim,
while denying the entirety of the employer’s $12 million counterclaim.
- Burland, Conyers & Marirea and Landmark
Restoration, Inc., Bermuda, 1992 — Katz & Stone represented
Burland, Conyers & Marirea in an arbitration arising out of construction
of the new Bermuda Airport terminal. The dispute involved the default
termination of the specialty contractor for the roof. Working closely
with expert roofing consultants, Katz & Stone assisted the main
contractor in establishing the validity of the termination and reprocurement
costs to complete the defaulted specialty contractors’ work.
The form of contract is American Institute of Architects.
|